Bentonite Liners for Stormwater Wet Ponds & Wetlands

For engineers designing wet ponds, retention basins, and constructed stormwater wetlands that need a liner to hold the permanent pool or protect groundwater. Compare the liner criteria in seven state manuals, design a PondLock® soil-bentonite liner to meet them, and start from an editable guide specification.

A liner holds the permanent pool or protects groundwater

In the state stormwater manuals reviewed on this page, a liner does one of two jobs. It keeps enough water in a wet pond or wetland to sustain the permanent pool, or it limits infiltration where runoff could reach groundwater. Whether a liner is needed, and the thickness and permeability it must meet, are set by the state manual, permit, or local review authority for the site.

This is not the NRCS framework. Our published bentonite application rates trace to NRCS Conservation Practice Standard 520, whose Table 3 gives minimum rates for clean water ponds. The stormwater documents below state their requirements as liner thickness and permeability. None of them gives a bentonite application rate.

Conditions that trigger a liner

  • Karst. Maryland's September 2025 draft states that "a liner shall be provided in karst topography." Iowa's manual states that in karst "a bentonite or clay liner or a synthetic impermeable liner should be provided." Virginia's regulation allows stormwater impoundments in karst areas only after a study of the area's geology and hydrology, and in karst features only after a geotechnical investigation (9VAC25-875-650).
  • Permeable soils, gravel, or fractured bedrock. New York's 2024 manual requires an impermeable liner where underlying soils infiltrate faster than 0.014 inch/hr or consist of gravel or fractured bedrock. Delaware's 2026 draft states that most hydrologic soil group A and B soils "will not support a permanent pool without the use of a liner."
  • Hotspot runoff and groundwater protection. Maryland's 2025 draft requires a liner for hotspot runoff. Wisconsin's liner flowchart considers industrial land use, fueling and vehicle maintenance areas, and local well or groundwater protection. Texas calls for impermeable liners on water quality basins over the Edwards Aquifer recharge zone.
  • No geotechnical data. New York requires a liner when geotechnical testing is not performed.
  • A professional recommendation. Delaware's 2026 draft requires a liner whenever a licensed geotechnical engineer or geologist recommends one. A designer who departs from that recommendation must submit a signed and sealed letter of justification.

Not every state sets liner criteria. North Carolina's current wet pond chapter, revised November 23, 2020, dropped the earlier manual's rule that the permanent pool be within 6 inches of the seasonal high water table or a liner be provided. Its comparison of old and new criteria now reads "No requirements regarding SHWT."

What seven state manuals require

Each row was checked against the agency's own document. Criteria are shown as published, including test-method designations. Drafts are labeled and may change before adoption.

Table 1. Liner requirements for stormwater wet ponds and constructed wetlands, by state, as published in each agency's document.
State & documentWhen a liner is required or recommendedLiner criteriaBentonite named?
MarylandMDE Stormwater Design Manual (2000, revised 2009), Ch. 3, §3.1.2 “Pond Liners,” p. 3.10 “May be needed” in karst topography, gravelly sands, or fractured bedrock to sustain a permanent pool, where geotechnical tests confirm the need. 6–12 in of clay soil, minimum 15% passing the #200 sieve, maximum permeability 1×10−5 cm/s; 30 mil poly-liner; bentonite; chemical additives; or other materials approved by the review authority. Yes. Listed as an option, with no material criteria.
MarylandDraft Chapter 3 update (September 19, 2025), §3.0.4.2 “Liners”
Draft
“Shall be provided” in karst topography and for hotspot runoff. May be needed in gravelly sands or fractured bedrock. Clay at least 12 in thick, minimum 15% passing the #200 sieve, maximum permeability 1×10−5 cm/s; or geomembrane. No. Liners “may be either clay or geomembrane.”
New YorkNYSDEC Stormwater Management Design Manual (July 31, 2024), §6.1.4.1 and Table 6.3 (ponds, p. 6-10); §6.2.4.1 (wetlands, p. 6-28) “Shall be required” where underlying soils infiltrate faster than 0.014 inch/hr, geotechnical testing is not performed, or soils are gravel or fractured bedrock. 12–24 in of clay soil, minimum 50% passing the #200 sieve, maximum permeability 1×10−5 cm/s; or 40 mil HDPE geomembrane. Installed over the entire wetted perimeter and at least 12 in above the permanent pool; for wetlands, every treatment cell, berm, and weir. No. The 2015 edition listed bentonite as an option.
TexasTCEQ RG-348, Edwards Aquifer (revised July 2005), §3.4.2, p. 3-38, as revised by the March 28, 2009 errata “Should be used” for retention, extended detention, wet pond, and constructed wetland basins over the recharge zone and where groundwater contamination is possible. Basins on the contributing zone need not have impermeable liners. Compacted clay at least 12 in thick per Table 3-6: permeability 1×10−6 cm/s (ASTM D-2434); plasticity index ≥15; liquid limit ≥30; clay particles passing ≥30%; 95% standard Proctor. Also allows GCL (<5×10−9 cm/s by ASTM D5887, 12 in cover recommended), concrete, or geomembrane (≥30 mil, UV resistant). Only in GCLs, which are described as typically consisting of bentonite clay.
WisconsinWDNR Technical Standard 1001, Wet Detention Pond (10/07), Appendix D Set by a liner flowchart: in-situ soil permeability to 3 ft below the pond bottom, local well or groundwater protection, industrial land use, fueling or vehicle maintenance areas, and dirty source areas. Type B at minimum where bedrock separation criteria are not met; Type A where bedrock is blasted. Type A clay: ≥50% fines, in-place ≤1×10−7 cm/s, average liquid limit ≥25, average PI ≥12, at least 2 ft thick. Type B clay: ≤1×10−6 cm/s, at least 2 ft thick. HDPE, GCL, and polyethylene options by type. All liners extend to the 2-yr, 24-hour storm elevation. Excluded from Type A clay (“natural soil, not bentonite”). GCL is accepted for Type A. Type B and C list “Clay” without that note.
IowaIowa Stormwater Management Manual, §9.11 Wet Detention Ponds (issued December 31, 2019) “Should be provided” in karst. Needed where native soils are not sufficient to create an adequate liner. No numeric criteria. “Consult a geotechnical engineer or a soil scientist on a case-by-case basis for final design.” Contract documents define the liner type and installation. Yes. “Bentonite materials and synthetic liners can sustain the permanent pool.”
DelawareDNREC BMP Standards & Specifications 13.0 Wet Ponds, 2026 public-notice draft (WSS20260001)
Draft
“Shall be required when recommended by a licensed, professional geotechnical engineer or geologist.” Every wet pond is evaluated for the need. Clay at least 12 in compacted, with 12 in of compacted soil above: permeability 1×10−6 cm/s (ASTM D-2434); PI ≥15%; liquid limit ≥30%; clay particles ≥30%; 95% standard Proctor. Or a 30 mil poly-liner, or other measures a qualified geotechnical professional recommends. No. Eligible as “other acceptable measures.”
North CarolinaNCDEQ Stormwater Design Manual, C-3 Wet Pond (revised November 23, 2020) Current criteria: “No requirements regarding SHWT.” The archived manual required the permanent pool within 6 in of the seasonal high water table “or a liner shall be provided.” None stated in C-3. No.

Confirm the governing edition. Manuals change: New York's 2024 manual dropped the bentonite option its 2015 edition listed, and Maryland and Delaware have drafts in review. Local governments can add requirements. Wisconsin's standard, for example, asks designers to consult the local community about wellhead and source water protection areas. Confirm the edition, criteria, and accepted test methods with the reviewing authority.

Design a soil-bentonite liner that meets clay-liner criteria

Where a manual names bentonite, as Maryland's 2009 manual and Iowa's do, a soil-bentonite liner is a listed option, but neither gives material criteria. Where a manual sets clay-liner criteria without naming bentonite, a soil-bentonite liner has to show it meets the same thickness and permeability. The reviewing authority then decides whether to accept it as a clay liner or under the manual's alternative-materials provision. In both cases the defensible specification is the same: a laboratory-tested blend of the site soil and the bentonite proposed for use, built to stated criteria.

  1. Identify the governing criterion. Record the jurisdiction, manual edition and section, minimum thickness, maximum permeability and test method, any index-property limits, and how far the liner must extend. In the manuals above, the permeability limit ranges from 1×10−5 cm/s (Maryland, New York) to 1×10−6 cm/s (Texas, the Delaware draft, Wisconsin Type B) to 1×10−7 cm/s (Wisconsin Type A).
  2. Check every row, not just permeability. Texas Table 3-6 and the Delaware draft also set plasticity index, liquid limit, and percent clay particles, limits written for natural clay. Test a blend of site soil and bentonite against each row. Where one does not fit, submit the laboratory data under the manual's alternative provision: Maryland's “other suitable materials approved by the appropriate review authority,” Delaware's “other acceptable measures as recommended by a qualified geotechnical professional,” or Iowa's case-by-case geotechnical review. In Wisconsin, Type A clay excludes bentonite; there, the bentonite-based Type A option is a GCL.
  3. Set the application rate in the laboratory. Blend representative site soil with the bentonite proposed for use at trial rates, compact the specimens to the specified density and moisture, and test hydraulic conductivity by the method the reviewing authority accepts. The design rate is the rate that meets the criterion with the margin the Engineer selects. NRCS CPS 520 takes the same approach for ponds: where laboratory data exist, the rate and lift thickness come from the geotechnical report. See NRCS minimum rates and their lift basis.
  4. Extend the liner where the water goes. New York requires the liner over the entire wetted perimeter and at least 12 in above the permanent pool, including every wetland cell, berm, and weir. Wisconsin requires all liners to reach the 2-year, 24-hour storm elevation. Texas's example installation keys the liner in above the basin's maximum water level.
  5. Cover it and plan for maintenance. The Delaware draft calls for 12 in of compacted soil over a clay liner, and Texas recommends 12 in of cover over a GCL. Wisconsin's operation and maintenance criteria call for showing how the liner will be protected during sediment removal and repair. Texas's 2017 addendum, in its batch detention basin guidance, cautions against compromising the basin lining during maintenance. Iowa directs that the liner not be disturbed during finish grading and be protected from erosion until the pond fills to its normal pool.
  6. Document the construction. Iowa's construction observation guidance calls for verifying that the liner was built to the construction documents and collecting the test results that document it.

The numbers line up in New York. New York's water-balance equation uses a monthly infiltration loss of “10.1 inches per Impermeable Liner Design Specifications.” By our arithmetic, not the manual's, 0.014 inch/hr is about 9.9×10−6 cm/s, essentially the 1×10−5 cm/s clay-liner limit, and 0.014 inch/hr over 30 days is about 10.1 inches. The liner trigger, the liner permeability, and the water-balance allowance describe the same rate.

The bentonite

PondLock® is natural Wyoming sodium bentonite with no additives, a Free Swell Index of 30 mL/2 g by ASTM D5890, and a granular gradation of 100% passing the No. 8 sieve with no more than 12% passing the No. 200 sieve. The granular form is intended for mechanical spreading and mixing in open-air earthwork. See the material specification and the mixed-method installation procedure.

Budget tonnage before the laboratory rate is known

For bids and early budgets, these figures give a starting tonnage before blend testing is complete. They are PondLock design ranges per 6-inch compacted lift, which meet or exceed the NRCS CPS 520 Table 3 minimums for clean water ponds. They are not shown to meet any stormwater permeability limit, and they do not replace the laboratory-determined rate.

Table 2. Preliminary estimating figures only, in lb of bentonite per ft² of lined area. A 12-inch liner is two 6-inch lifts; a 24-inch liner is four.
Soil classificationPer 6″ lift12″ liner (2 lifts)24″ liner (4 lifts)
Silts and clayey silts2 – 34 – 68 – 12
Silty sands3 – 56 – 1012 – 20
Clean sands and gravelly soils5 – 6+10 – 12+20 – 24+

The lined area includes the side slopes up to the liner's top elevation, which can sit above the permanent pool. For a quick quantity, the bentonite calculator derives slope area from the surface area, depth, and side slope. Enter the area and depth at the liner's top elevation and the full liner thickness.

Soil-bentonite liner for stormwater wet ponds and wetlands

Edit the [bracketed] items for the project. This guide specification is a starting point for the Engineer of Record. It does not establish compliance with any jurisdiction's requirements, and none of the state documents above names PondLock.

Part 1 — General

  1. Scope. Furnish and install a compacted soil-bentonite liner for [wet pond / constructed stormwater wetland — facility name], including [forebays, treatment cells, berms, and weirs] within the lined area shown on the drawings.
  2. Governing criteria. The completed liner shall meet the requirements of [jurisdiction, manual, edition, and section]:
    1. Minimum compacted thickness: [__ inches].
    2. Maximum hydraulic conductivity: [__ cm/s], by [test method accepted by the reviewing authority].
    3. Index properties, where required: [plasticity index, liquid limit, percent fines or clay particles, with test methods].
  3. Extent. Line [the entire wetted perimeter] to elevation [__], [not less than __ inches above the permanent pool / the 2-year, 24-hour storm elevation / as required by the governing criteria].
  4. Acceptance as a liner. [Where the governing document does not name soil-bentonite liners:] Submit the laboratory blend report to [reviewing authority] and obtain acceptance before construction.
  5. Submittals.
    1. Bentonite manufacturer's certification of free swell (ASTM D5890), gradation, and moisture content for the material to be delivered.
    2. Laboratory blend report establishing the application rate, prepared with representative site or borrow soil and the bentonite proposed for use.
    3. Placement, mixing, and compaction equipment and procedures.
    4. Field quality-control results and as-built liner elevations and thickness.

Part 2 — Products

  1. Bentonite. Natural sodium bentonite (sodium montmorillonite), with no additives, polymers, or chemical treatment.
    1. Free Swell Index: not less than [22 mL/2 g; 25 mL/2 g preferred] by ASTM D5890.
    2. Gradation: 100% passing the No. 8 sieve; not more than 12% passing the No. 200 sieve.
    3. Moisture content: not more than 20% at delivery.
    4. Basis of design: PondLock® granular sodium bentonite, Natural Waterscapes [, or approved equal meeting this article].
  2. Soil. [On-site / borrow] soil matching the soil used in the laboratory blend report, free of organic matter, debris, and rocks larger than 1 inch.
  3. Application rate. [__ lb/ft² per __-inch compacted lift / __% by dry weight of soil], as established by the approved laboratory blend report. A change in soil source requires a new blend test.

Part 3 — Execution

  1. Subgrade. Strip vegetation, roots, topsoil, and organic matter. Remove rocks larger than 1 inch. Shape to grade, scarify, and proof-roll; remove and replace areas that pump or rut.
  2. Placement and mixing. Spread bentonite uniformly at the approved rate with mechanical spreaders. Mix to the full lift depth in multiple passes until color and texture are uniform. Do not place bentonite in high wind, rain, or on a saturated surface.
  3. Moisture and compaction. Place the amended soil in lifts not exceeding [6] inches [compacted]. Condition to [the moisture range used in the laboratory blend report] and compact to not less than [95]% of standard Proctor maximum dry density.
  4. Cover and protection. Place [__ inches] of compacted soil cover over the completed liner [within __ hours of completing each area]. Protect the liner from drying, erosion, and equipment traffic until the facility is filled to its permanent pool. Repair disturbed areas with the same materials and procedures.
  5. Connections. Tie the liner to inlets, outlet structures, and penetrations as detailed on the drawings.
  6. Quality control. Test field density and moisture at [__ per __ ft² per lift]. Verify thickness at [__ locations]. Take samples for laboratory hydraulic conductivity at [__ per __ ft²]. Rework and retest areas that fail.
  7. Records and maintenance. Record liner and cover elevations on the as-built drawings. Show in the operation and maintenance plan how the liner will be protected during sediment removal and repair.

Bring the basin design into the quote

Share what is available at your current design or bid stage. Mark preliminary quantities and pending tests so the supply quote reflects the project's status.

Site & geotechnical data

Project location, soil borings and classifications, infiltration or permeability test results, seasonal high water table, karst or bedrock findings, and whether the facility receives hotspot or industrial runoff.

Governing criteria

Jurisdiction, manual edition and section, required liner thickness and permeability, index-property limits, liner extent elevation, and whether soil-bentonite is named or will be submitted as an alternative.

Quantity & schedule

Lined area including side slopes and cells, number of lifts, laboratory rate or its testing status, delivery ZIP code, bid deadline, delivery window, and any phased releases.

Keep the quantity basis explicit. State whether a rate is per lift or for the full liner thickness, and whether it is in lb/ft² of lined area or percent by dry weight of soil. Converting percent by weight to tonnage requires the project's density data.

Plan deliveries around the earthwork

PondLock ships in 2,000 lb and 3,000 lb bulk sacks for liner-scale work. Include total tonnage and the expected sequence of lined areas so we can review packaging, freight, and timing for your location.

  • Identify unloading equipment, site access, and receiving hours.
  • Describe storage conditions and staging areas available on site.
  • List required material certifications and submittal deadlines.
  • Confirm availability, freight, and delivery timing as part of the quote.

Use the quote form to summarize the project. Send plans, specifications, and geotechnical reports to support@naturalwaterscapes.com with the same project name. A supply quote does not establish design approval or liner performance.

State stormwater manuals cited on this page

Maryland Department of the Environment — 2000 Maryland Stormwater Design Manual, Volumes I & II (revised May 2009). Chapter 3, Section 3.1.2, “Pond Liners,” printed page 3.10. Read Chapter 3.

Maryland Department of the Environment — Draft Updates to Maryland's Stormwater Design Manual, Chapter 3 (September 19, 2025). Section 3.0.4.2, “Liners.” Draft. Read the draft chapter.

New York State Department of Environmental Conservation — New York State Stormwater Management Design Manual (July 31, 2024). Section 6.1.4.1 and Table 6.3, Stormwater Ponds (printed page 6-10); Section 6.2.4.1, Stormwater Wetlands (printed page 6-28); pond water-balance equation. Read the manual.

Texas Commission on Environmental Quality — RG-348, Complying with the Edwards Aquifer Rules: Technical Guidance on Best Management Practices (revised July 2005). Section 3.4.2, “Basin Lining Requirements,” and Table 3-6, page 3-38. Read RG-348. Section 3.4.2 as revised by the errata sheet of March 28, 2009; maintenance caution from the addendum sheet of January 20, 2017.

Wisconsin Department of Natural Resources — Technical Standard 1001, Wet Detention Pond (10/07). Liner criteria in the design section and Appendix D, “Pond Liner Design, Decision Flowchart.” Read the standard.

Iowa Department of Natural Resources — Iowa Stormwater Management Manual, Section 9.11, Wet Detention Ponds (issued December 31, 2019). Site feasibility (soils and minimum depth to water table) and construction steps. Read Section 9.11.

Delaware Department of Natural Resources and Environmental Control — BMP Standards and Specifications 13.0, Wet Ponds, 2026 public-notice draft (WSS20260001). Design criteria, “Liners.” Draft. Read the draft.

North Carolina Department of Environmental Quality — Stormwater Design Manual, C-3 Wet Pond (revised November 23, 2020). “Old Versus New Design Standards.” Read C-3.

Virginia Administrative Code — 9VAC25-875-650, Stormwater management impoundment structures or facilities (effective July 1, 2024). Karst study and geotechnical investigation requirements. Read the regulation.

These documents describe each jurisdiction's requirements. None of them evaluates or approves PondLock. Liner design, material acceptance, and performance are determined by the Engineer of Record and the reviewing authority for each project.